Bogdanci wind turbines
Bogdanci wind turbines | |
---|---|
Country | Macedonia |
Location | Bogdanci |
Coordinates | 41°13′43″N 22°33′47″E / 41.22872°N 22.563°E |
Construction began | 18 May 2013 |
Construction cost | EUR 55.5 million |
Owner | Elektrani na Makedonija |
Bogdanci wind turbines park ( PVE Bogdanci), also known as Wind park „Bogdanci“) is a wind park near the town Bogdanci, North Macedonia. Its construction began in May 2013 and was finished in February 2014. The wind turbines began commercial operations within North Macedonia's electricity distribution network on 21 March 2014.
Location
[edit]The Bogdanci wind turbines park is located near the town Bogdanci, on the Ranavec hill which rises above Bogdanci. It covers an area of 29 hm2 (347,000 sq yd).
Building
[edit]First stage
[edit]The first stage of the project ended in February 2014 after all of the 16 planned wind turbines were raised up and completed, while in March 2014 they were connected to the MEPSO distribution network.[1][2] After connecting followed test trials, after which the commercial operations began.
During March 2014, the road infrastructure, power line connections, command building, and the 20/110 kW electrical substation were also finished.[3] The total cost for building the wind park was EUR 55.5 million, of which EUR 47.9 million (86.3%) were borrowed from Germany through KfW Bank, while the remaining EUR 7.6 million (13.7%) were taken from Elektrani na Makedonija's own budget.
Stage 2
[edit]In the second stage of the project, six additional wind turbines shall be added, which will increase the installed power to 50 MW, resulting in an annual green energy production of 125 GW·h.[4]
Commercial operations
[edit]The test period started with the wind park's connection to the Macedonian electricity distribution system, and after it had been completed, the wind turbines entered the commercial operations phase. The wind turbines were connected to the electricity distributional network on 21 March 2014.[5][6] Until 10 August 2014, the wind park delivered 31 GW·h of electricity, which is one third of its planned 100 GW·h annual production, sufficient for providing a city with a population of 60,000 with electricity.
Gallery
[edit]References
[edit]- ^ "Заврши монтажата на ветерниците во Богданци, наскоро во производство". Дневник (in Macedonian). МПМ Македонија. 21 March 2014. Retrieved 17 January 2015.
- ^ "Се исправија првите ветерници во Македонија". Нова Македонија (in Macedonian). Retrieved 17 January 2015.
- ^ "Ветерниците во Богданци наскоро ќе прават струја". Дневник (in Macedonian). МПМ Македонија. 21 March 2014. Archived from the original on 4 March 2016. Retrieved 17 January 2015.
- ^ "Обезбедени средства за втората фаза од изградбата на ветропаркот "Богданци"". build.mk. Retrieved 2018-12-14.[permanent dead link]
- ^ "Утре се приклучуваат ветерните електрани во мрежата на ЕВН, четири града два часа без струја". Дневник (in Macedonian). МПМ Македонија. 19 March 2014. Archived from the original on 21 March 2014. Retrieved 17 January 2015.
- ^ "Ветерниот парк "Богданци" испорача 31 милион квч струја". Дневник (in Macedonian). Скопје: МПМ Македонија. 10 August 2014. Archived from the original on 12 August 2014. Retrieved 17 January 2015.
External links
[edit]- Енергија од ветер, ЕСМ
- „Повеќе за ветерниот парк 'Богданци'“ Archived 2014-02-03 at the Wayback Machine, „Енергетска ефикасност“, 20 May 2013.